Process-Scheduling

Question 4

Four jobs to be executed on a single processor system arrive at time 0+ in the order A, B, C, D. their burst CPU time requirements are 4, 1, 8, 1 time units respectively. The completion time of A under round robin scheduling with time slice of one time unit is

A
10
B
4
C
8
D
9
Question 4 Explanation: 
Time quantum is 1 unit.

∴ Completion time of A is 9 unit.
Correct Answer: D
Question 4 Explanation: 
Time quantum is 1 unit.

∴ Completion time of A is 9 unit.