Question 1

Consider the following set of processes, assumed to have arrived at time 0. Consider the CPU scheduling algorithms Shortest Job First (SJF) and Round Robin (RR). For RR, assume that the processes are scheduled in the order P1,P2,P3,P4.

If the time quantum for RR is 4 ms, then the absolute value of the difference between the average turnaround times (in ms) of SJF and RR (round off to 2 decimal places) is _____.

A
5.25
Question 1 Explanation: 
SJF:

Turn Around Time = (21 – 0) + (13 – 0) + (2 – 0) + (6 – 0), Average = 42/4 = 10.50

Turn Around Time (TAT) = (18 – 0) + (21 – 0) + (10 – 0) + (14 – 0), Average = 63/4 = 15.75
Absolute difference = |10.50-15.75| = 5.25
Correct Answer: A
Question 1 Explanation: 
SJF:

Turn Around Time = (21 – 0) + (13 – 0) + (2 – 0) + (6 – 0), Average = 42/4 = 10.50

Turn Around Time (TAT) = (18 – 0) + (21 – 0) + (10 – 0) + (14 – 0), Average = 63/4 = 15.75
Absolute difference = |10.50-15.75| = 5.25
0 0 votes
Article Rating
Subscribe
Notify of
0 Comments
Inline Feedbacks
View all comments
0
Would love your thoughts, please comment.x
()
x
error: Alert: Content selection is disabled!!