Given CPU time slice of 2ms and following list of processes.
Find average turnaround time and average waiting time using round robin CPU scheduling?
Correct Answer: B
Question 784 Explanation:
Average Turnaround Time= (5+5+7)/3
= 5.66
Average Waiting Time= (2+1+2)/3
= 1.66
4.0
5.66, 1.66
5.66, 0
7, 2