In Activity – Selection problem, each activity ai has a start time si and a finish time fi where si ≤ fi. Activities ai and aj are compatible if:

Correct Answer: C

Question 16 Explanation: 
Each activity ai has a start time si and a finish time fi where 0 ≤ si < fi < ∞. If selected, activity ai takes place during the half-open time interval [ si , fi ]. Activities ai and aj are compatible if the intervals [ si , fi ] and [ sj , fj ] do not overlap. That is, ai and aj are compatible if si ≥ fj or sj ≥ fi. In the activity-selection problem, we wish to select a maximum-size subset of mutually compatible activities.
A
si ≥ fj
B
sj ≥ fi
C
si ≥ fj or sj ≥ fi
D
si ≥ fj and sj ≥ fi