| Question 2 |
Which of the following are Agile Process Models ?
(A) Extreme Programming (XP)
(B) Waterfall
(C) Scrum
(D) Spiral
(E) Incrementa
l
Choose the correct answer from the options given below :
(A) Extreme Programming (XP)
(B) Waterfall
(C) Scrum
(D) Spiral
(E) Incrementa
l
Choose the correct answer from the options given below :
| (A) and (C) only
| |
| (B) and (C) only
| |
| (A) and (D) Only
| |
| (B) and (E) only
|
Question 2 Explanation:
Extreme Programming (XP) and Scrum are both Agile Process Models.
XP (Extreme Programming) focuses on technical practices and customer satisfaction.
Scrum is a framework that organizes the work into sprints and promotes iterative progress.
The other options listed are not strictly considered Agile:
Waterfall is a traditional, linear project management method.
Spiral is a risk-driven process model that combines elements of both iterative development and the Waterfall model.
Incremental is an approach used in Agile but is not itself a specific Agile process model.
So, the correct choice is (A) and (C) only.
XP (Extreme Programming) focuses on technical practices and customer satisfaction.
Scrum is a framework that organizes the work into sprints and promotes iterative progress.
The other options listed are not strictly considered Agile:
Waterfall is a traditional, linear project management method.
Spiral is a risk-driven process model that combines elements of both iterative development and the Waterfall model.
Incremental is an approach used in Agile but is not itself a specific Agile process model.
So, the correct choice is (A) and (C) only.
Correct Answer: A
Question 2 Explanation:
Extreme Programming (XP) and Scrum are both Agile Process Models.
XP (Extreme Programming) focuses on technical practices and customer satisfaction.
Scrum is a framework that organizes the work into sprints and promotes iterative progress.
The other options listed are not strictly considered Agile:
Waterfall is a traditional, linear project management method.
Spiral is a risk-driven process model that combines elements of both iterative development and the Waterfall model.
Incremental is an approach used in Agile but is not itself a specific Agile process model.
So, the correct choice is (A) and (C) only.
XP (Extreme Programming) focuses on technical practices and customer satisfaction.
Scrum is a framework that organizes the work into sprints and promotes iterative progress.
The other options listed are not strictly considered Agile:
Waterfall is a traditional, linear project management method.
Spiral is a risk-driven process model that combines elements of both iterative development and the Waterfall model.
Incremental is an approach used in Agile but is not itself a specific Agile process model.
So, the correct choice is (A) and (C) only.