...
Software-Engineering
November 9, 2023
Question 2070 – Nielit Scientific Assistance CS 15-10-2017
November 9, 2023
Software-Engineering
November 9, 2023
Question 2070 – Nielit Scientific Assistance CS 15-10-2017
November 9, 2023

Question 2069 – Nielit Scientific Assistance CS 15-10-2017

If P is risk probability, L is loss, then is computed as

Correct Answer: C

Question 13 Explanation: 
Risk Exposure(RE) is determined using the following relationship
RE = P*L
where P is the probability of occurrence for a risk, and L is the cost to the project should the risk occur.
A
RE=P/L
B
RE=P+L
C
RE=P*L
D
RE=2*P*L
0 0 votes
Article Rating
Subscribe
Notify of
0 Comments
Inline Feedbacks
View all comments
0
Would love your thoughts, please comment.x
()
x