Question 2069 – Nielit Scientific Assistance CS 15-10-2017

If P is risk probability, L is loss, then is computed as

Correct Answer: C

Question 13 Explanation: 
Risk Exposure(RE) is determined using the following relationship
RE = P*L
where P is the probability of occurrence for a risk, and L is the cost to the project should the risk occur.
A
RE=P/L
B
RE=P+L
C
RE=P*L
D
RE=2*P*L