Question 5126 – UGC NET CS 2018 JUNE Paper-2
December 1, 2023Question 5130 – UGC NET CS 2018 JUNE Paper-2
December 1, 2023Question 5129 – UGC NET CS 2018 JUNE Paper-2
Assume the following regarding the development of a software system P:
– Estimated lines of code of P : 33, 480 LOC
– Average productivity for P : 620 LOC per person-month
– Number of software developers : 6
– Average salary of a software developer : 50,000 per month
If E, D and C are the estimated development effort (in person-months), estimated development time (in months), and estimated development cost (in Lac) respectively, then (E, D, C) =
Correct Answer: B
Question 11 Explanation:
– Estimated lines of code of P : 33480 LOC
– Average productivity for P : 620 LOC per person-month
– Number of software developers : 6
– Average salary of a software developer : 50000 per month
Step-1: Estimated development effort (in person-months)= 33480 /620
E=54
Step-2: Estimated development time (in months) =54/6
D= 9 months
Step-3: Estimated development cost (in Lac) = 50000*6*9
=27 lacs
– Average productivity for P : 620 LOC per person-month
– Number of software developers : 6
– Average salary of a software developer : 50000 per month
Step-1: Estimated development effort (in person-months)= 33480 /620
E=54
Step-2: Estimated development time (in months) =54/6
D= 9 months
Step-3: Estimated development cost (in Lac) = 50000*6*9
=27 lacs
(48, 8, 24)
(54, 9, 27)
(60, 10, 30)
(42, 7, 21)