Question 733 – Software-Engineering

Which of the following is not a maturity level as per the Capability Maturity Model?

Correct Answer: B

Question 85 Explanation: 
Capability Maturity Model levels

1. Initial

2. Repeatable

3. Defined

4. Managed

5. Optimized
A
Initial
B
Measurable
C
Repeatable
D
Optimized