Match the 5 CMM Maturity levels/CMMI staged representations in List-I with their characterizations in List-II :
List-I List-II (a) Initial (i) Processes are improved quantitatively and continually. (b) Repeatable (ii) The plan for a project comes from a template for plans. (c) Defined (iii) The plan uses processes that can be measured quantitatively. (d) Managed (iv) There may not exist a plan or it may be abandoned. (e) Optimizing (v) There’s a plan and people stick to it.
Code :
Correct Answer: D
Question 96 Explanation:
Initial Stage: There may not exist a plan or it may be abandoned.
Repeatable: There’s a plan and people stick to it.
Defined: The plan for a project comes from a template for plans.
Managed: The plan uses processes that can be measured quantitatively.
Optimizing: Processes are improved quantitatively and continually.
Repeatable: There’s a plan and people stick to it.
Defined: The plan for a project comes from a template for plans.
Managed: The plan uses processes that can be measured quantitatively.
Optimizing: Processes are improved quantitatively and continually.
![](https://solutionsadda.in/wp-content/uploads/2019/03/a5.jpg)
(a)-(iv), (b)-(v), (c)-(i), (d)-(iii), (e)-(ii)
(a)-(i), (b)-(ii), (c)-(iv), (d)-(v), (e)-(iii)
(a)-(v), (b)-(iv), (c)-(ii), (d)-(iii), (e)-(i)
(a)- (iv), (b)-(v), (c)-(ii), (d)-(iii), (e)-(i)