Question 424

Match the 5 CMM Maturity levels/CMMI staged representations in List-I with their characterizations in List-II :

    List-I  List-II (a) Initial  (i) Processes are improved quantitatively and continually.  (b) Repeatable  (ii) The plan for a project comes from a template for plans.  (c) Defined  (iii) The plan uses processes that can be measured quantitatively.  (d) Managed  (iv) There may not exist a plan or it may be abandoned.  (e) Optimizing  (v) There’s a plan and people stick to it.

Code :

 

A
(a)-(iv), (b)-(v), (c)-(i), (d)-(iii), (e)-(ii)
B
(a)-(i), (b)-(ii), (c)-(iv), (d)-(v), (e)-(iii)
C
(a)-(v), (b)-(iv), (c)-(ii), (d)-(iii), (e)-(i)
D
(a)- (iv), (b)-(v), (c)-(ii), (d)-(iii), (e)-(i)
Question 424 Explanation: 
Initial Stage: There may not exist a plan or it may be abandoned.

Repeatable: There’s a plan and people stick to it.
Defined: The plan for a project comes from a template for plans.
Managed: The plan uses processes that can be measured quantitatively.
Optimizing: Processes are improved quantitatively and continually.
Correct Answer: D
Question 424 Explanation: 
Initial Stage: There may not exist a plan or it may be abandoned.

Repeatable: There’s a plan and people stick to it.
Defined: The plan for a project comes from a template for plans.
Managed: The plan uses processes that can be measured quantitatively.
Optimizing: Processes are improved quantitatively and continually.