Question 66
58000 LOC gaming software is developed with effort of 3 person-year. What is the productivity of person-month?
A
1.9 KLOC
B
1.6 KLOC
C
4.8 KLOC
D
4.2 KLOC
Question 66 Explanation: 
Productivity= KLOC/ effort
Productivity=58/12*3
=1.61 KLOC (approximately)
Correct Answer: B
Question 66 Explanation: 
Productivity= KLOC/ effort
Productivity=58/12*3
=1.61 KLOC (approximately)