Question 11 |
Consider the following program segment for concurrent processing using semaphore operators P and V for synchronization. Draw the precedence graph for the statements S1 to S9.
var a, b, c, d, e, f, g, h, i, j, k : semaphore; begin cobegin begin S1; V(a); V(b) end; begin P(a); S2; V(c); V(d) end; begin P(c); S4; V(c) end; begin P(d); S5; V(f) end; begin P(e); P(f); S7; V(k) end; begin P(b); S3;V(g);V(h) end; begin P(g); S6; V(i) end; begin P(h); P(i); S8; V(j) end; begin P(j); P(j); P(k); S9 end; coend end;
Theory Explanation. |
Correct Answer: A