Question 17
|
Consider the program given below, in a block-structured pseudo-language with lexical scoping and nesting of procedures permitted.
Program main; Var ... Procedure A1; Var ... Call A2; End A1 Procedure A2; Var ... Procedure A21; Var ... Call A1; End A21 Call A21; End A21 Call A1; End main.
Consider the calling chain : Main->A1->A2->A21->A1 The correct set of activation records along with their access links is given by:
Question 17 Explanation:
Main → A1 → A2 → A21 → A1
Since, Activation records are created at procedure exit time.
A1 & A2 are defined under Main ( ). So A1 & A2 access links are pointed to main.
A21 is defined under A2, hence its access link will point to A2.
Correct Answer: D
Question 17 Explanation:
Main → A1 → A2 → A21 → A1
Since, Activation records are created at procedure exit time.
A1 & A2 are defined under Main ( ). So A1 & A2 access links are pointed to main.
A21 is defined under A2, hence its access link will point to A2.