Question 259
Working software is not available until late in the process in
A
Waterfall model
B
Prototyping model
C
Incremental model
D
Evolutionary Development model
Question 259 Explanation: 
Waterfall Model: We can not go back in previous project phase as soon as as we proceed to next phase ,So inflexible
Advantages:
→Waterfall model is simple and easy to understand.
→It works as reference model for others.
Disadvantage:
→Real projects cannot be sequential
→Initially all requirements should known i.e requirements are frozen. It may be suited for static projects.
→Error omission too costly
→Maintenance is too costly(We have to redesign the whole project from scratch)
→Customer must have patience
→It is based on Big-Bang approach
Correct Answer: A
Question 259 Explanation: 
Waterfall Model: We can not go back in previous project phase as soon as as we proceed to next phase ,So inflexible
Advantages:
→Waterfall model is simple and easy to understand.
→It works as reference model for others.
Disadvantage:
→Real projects cannot be sequential
→Initially all requirements should known i.e requirements are frozen. It may be suited for static projects.
→Error omission too costly
→Maintenance is too costly(We have to redesign the whole project from scratch)
→Customer must have patience
→It is based on Big-Bang approach
0 0 votes
Article Rating
Subscribe
Notify of
0 Comments
Inline Feedbacks
View all comments
0
Would love your thoughts, please comment.x
()
x
error: Alert: Content selection is disabled!!