Problems with waterfall model are :

    1. Real projects rarely follow this model proposes
    2. It is often difficult for the customer
    3. Working model is available only in the end
    4. Developers are delayed unnecessarily

 

Which of the following is true :

A
1 and 4 only
B
2 and 3 only
C
1, 2 and 3 only
D
1, 2, 3 and 4
Question 194 Explanation: 
Problems with waterfall model are
1. Real projects rarely follow this model proposes
2. It is often difficult for the customer
3. Working model is available only in the end
4. Developers are delayed unnecessarily
Correct Answer: D
Question 194 Explanation: 
Problems with waterfall model are
1. Real projects rarely follow this model proposes
2. It is often difficult for the customer
3. Working model is available only in the end
4. Developers are delayed unnecessarily