Question 281 |
__________ are applied throughout the software process.
Framework activities | |
Umbrella activities | |
Planning activities | |
Construction activities |
Question 281 Explanation:
→ The umbrella activities occur throughout the software process they are applied evenly across the process, the analysis encompasses a set of work tasks (eg. requirement gathering,
elaboration, negotiation specification and validation).
→ These activities include Software project tracking and control, Risk management, Software quality assurance, and formal technical reviews, measurement, Software configuration
management, reusability management and work product preparation and production.
elaboration, negotiation specification and validation).
→ These activities include Software project tracking and control, Risk management, Software quality assurance, and formal technical reviews, measurement, Software configuration
management, reusability management and work product preparation and production.
Correct Answer: B
Question 281 Explanation:
→ The umbrella activities occur throughout the software process they are applied evenly across the process, the analysis encompasses a set of work tasks (eg. requirement gathering,
elaboration, negotiation specification and validation).
→ These activities include Software project tracking and control, Risk management, Software quality assurance, and formal technical reviews, measurement, Software configuration
management, reusability management and work product preparation and production.
elaboration, negotiation specification and validation).
→ These activities include Software project tracking and control, Risk management, Software quality assurance, and formal technical reviews, measurement, Software configuration
management, reusability management and work product preparation and production.