Software Risk estimation involves following two tasks :
|
risk magnitude and risk impact
|
|
|
risk probability and risk impact
|
|
|
risk maintenance and risk impact
|
|
|
risk development and risk impact
|
Question 289 Explanation:
Software Risk estimation involves risk probability and risk impact.
Correct Answer: B