UGC NET CS 2006 Dec-paper-2

Question 41
Software Cost Performance index (CPI) is given by :
[Where : BCWP stands for Budgeted Cost of Work Performed.
BCWS stands for Budget Cost of Work Scheduled
ACWP stands for Actual Cost of Work Performed
A
BCW P/ ACW P
B
No option given
C
BCWP−ACWP
D
BCWP−BCWS
Question 41 Explanation: 
The Cost Performance Index can be determined by dividing the earned value by actual cost.
Cost Performance Index = BCWP stands for Budgeted Cost of Work Performed / ACWP stands for Actual Cost of Work Performed
CPI = BCWP/ACWP
Correct Answer: A
Question 41 Explanation: 
The Cost Performance Index can be determined by dividing the earned value by actual cost.
Cost Performance Index = BCWP stands for Budgeted Cost of Work Performed / ACWP stands for Actual Cost of Work Performed
CPI = BCWP/ACWP