Question 41 |
Software Cost Performance index (CPI) is given by :
[Where : BCWP stands for Budgeted Cost of Work Performed.
BCWS stands for Budget Cost of Work Scheduled
ACWP stands for Actual Cost of Work Performed
[Where : BCWP stands for Budgeted Cost of Work Performed.
BCWS stands for Budget Cost of Work Scheduled
ACWP stands for Actual Cost of Work Performed
BCW P/ ACW P | |
No option given | |
BCWP−ACWP | |
BCWP−BCWS |
Question 41 Explanation:
The Cost Performance Index can be determined by dividing the earned value by actual cost.
Cost Performance Index = BCWP stands for Budgeted Cost of Work Performed / ACWP stands for Actual Cost of Work Performed
CPI = BCWP/ACWP
Cost Performance Index = BCWP stands for Budgeted Cost of Work Performed / ACWP stands for Actual Cost of Work Performed
CPI = BCWP/ACWP
Correct Answer: A
Question 41 Explanation:
The Cost Performance Index can be determined by dividing the earned value by actual cost.
Cost Performance Index = BCWP stands for Budgeted Cost of Work Performed / ACWP stands for Actual Cost of Work Performed
CPI = BCWP/ACWP
Cost Performance Index = BCWP stands for Budgeted Cost of Work Performed / ACWP stands for Actual Cost of Work Performed
CPI = BCWP/ACWP