Software-Engineering
August 28, 2024Software-Engineering
August 28, 2024Software-Engineering
|
Question 133
|
An __________ chart is a project schedule representation that presents project plan as a directed graph. The critical path is the __________ sequence of ______________ tasks and it defines project _______________
|
Activity, Shortest, Independent, Cost
|
|
|
Activity, Longest, Dependent, Duration
|
|
|
Activity, Longest, Independent, Duration
|
|
|
Activity, Shortest, Dependent, Duration
|
Question 133 Explanation:
The critical path method (CPM), or critical path analysis (CPA), is an algorithm for scheduling a set of project activities. It is commonly used in conjunction with the program evaluation and review technique (PERT). A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish
Correct Answer: B
Question 133 Explanation:
The critical path method (CPM), or critical path analysis (CPA), is an algorithm for scheduling a set of project activities. It is commonly used in conjunction with the program evaluation and review technique (PERT). A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish
