Question 12

Consider a software project with the following information domain characteristic for calculation of function point metric.

    Number of external inputs (I) = 30
    Number of external output (O) = 60
    Number of external inquiries (E) = 23
    Number of files (F) = 08
    Number of external interfaces (N) = 02

It is given that the complexity weighting factors for I, O, E, F and N are 4, 5, 4, 10 and 7, respectively. It is also given that, out of fourteen value adjustment factors that influence the development effort, four factors are not applicable, each of he other four factors have value 3, and each of the remaining factors have value 4. The computed value of function point metric is __________.

A
612.06
B
612.07
C
612.08
D
612.09
Question 12 Explanation: 
Note: Out of Syllabus.
Correct Answer: A
Question 12 Explanation: 
Note: Out of Syllabus.
0 0 votes
Article Rating
Subscribe
Notify of
0 Comments
Inline Feedbacks
View all comments
0
Would love your thoughts, please comment.x
()
x
error: Alert: Content selection is disabled!!