Question 766 – Software-Engineering
December 9, 2023
Question 809 – Software-Engineering
December 9, 2023
Question 766 – Software-Engineering
December 9, 2023
Question 809 – Software-Engineering
December 9, 2023

Question 808 – Software-Engineering

Match the 5 CMM Maturity levels/CMMI staged representations in List-I with their characterizations in List-II :

    List-I                                List-II
(a) Initial        (i) Processes are improved quantitatively and continually. 
(b) Repeatable    (ii) The plan for a project comes from a template for plans. 
(c) Defined      (iii) The plan uses processes that can be measured quantitatively. 
(d) Managed       (iv) There may not exist a plan or it may be abandoned. 
(e) Optimizing     (v) There’s a plan and people stick to it.

Code :

 

Correct Answer: D

Question 96 Explanation: 
Initial Stage: There may not exist a plan or it may be abandoned.

Repeatable: There’s a plan and people stick to it.
Defined: The plan for a project comes from a template for plans.
Managed: The plan uses processes that can be measured quantitatively.
Optimizing: Processes are improved quantitatively and continually.
A
(a)-(iv), (b)-(v), (c)-(i), (d)-(iii), (e)-(ii)
B
(a)-(i), (b)-(ii), (c)-(iv), (d)-(v), (e)-(iii)
C
(a)-(v), (b)-(iv), (c)-(ii), (d)-(iii), (e)-(i)
D
(a)- (iv), (b)-(v), (c)-(ii), (d)-(iii), (e)-(i)
0 0 votes
Article Rating
Subscribe
Notify of
0 Comments
Inline Feedbacks
View all comments
0
Would love your thoughts, please comment.x
()
x
error: Alert: Content selection is disabled!!