Question 299
Sliding window concept of software project management is :
A
Preparation of comprehensible plan
B
Preparation of the various stages of development
C
Ad-hoc planning
D
Requirement analysis
Question 299 Explanation: 
→ In the sliding window technique, starting with an initial plan, the project is planned more accurately in successive development stages.
→ At the start of a project, project managers have incomplete knowledge about the details of the project. Their information base gradually improves as the project progresses through different phases. After the completion of every phase, the project managers can plan each subsequent phase more accurately and with increasing levels of confidence.
Correct Answer: A
Question 299 Explanation: 
→ In the sliding window technique, starting with an initial plan, the project is planned more accurately in successive development stages.
→ At the start of a project, project managers have incomplete knowledge about the details of the project. Their information base gradually improves as the project progresses through different phases. After the completion of every phase, the project managers can plan each subsequent phase more accurately and with increasing levels of confidence.