Question 134
Match the Agile Process models with the task performed during the model:


Choose the correct option from those given below:

A
(a)-(ii), (b)-(iv), (c)-(i), (d)-(iii)
B
(a)-(i), (b)-(iii), (c)-(ii), (d)-(iv)
C
(a)-(i), (b)-(iv), (c)-(ii), (d)-(iii)
D
(a)-(i), (b)-(iv), (c)-(ii), (d)-(iii)
Question 134 Explanation: 
Scrum → Sprint backlog
Adaptive software development → Time box release plan
Extreme programming → CRC cards
Feature-driven development → < action > the < result > < by / for / of / to > a(n) < object >
Correct Answer: A
Question 134 Explanation: 
Scrum → Sprint backlog
Adaptive software development → Time box release plan
Extreme programming → CRC cards
Feature-driven development → < action > the < result > < by / for / of / to > a(n) < object >
0 0 votes
Article Rating
Subscribe
Notify of
0 Comments
Inline Feedbacks
View all comments
0
Would love your thoughts, please comment.x
()
x
error: Alert: Content selection is disabled!!