Question 144
|
Which of the following are the primary objectives of risk monitoring in software project tracking?
P: To assess whether predicted risks do, in fact, occur
Q: To ensure that risk aversion steps defined for the risk are being properly applied
R: To collect information that can be used for future risk analysis
P: To assess whether predicted risks do, in fact, occur
Q: To ensure that risk aversion steps defined for the risk are being properly applied
R: To collect information that can be used for future risk analysis
|
Only P and Q
|
|
|
Only P and R
|
|
|
Only Q and R
|
|
|
All the P,Q,R
|
Question 144 Explanation:
Risk monitoring is a project tracking activity with three primary objectives:
(1) to assess whether predicted risks occur.
(2) to ensure that risk aversion steps defined for the risk are being properly applied; and
(3) to collect information that can be used for future risk analysis.
(1) to assess whether predicted risks occur.
(2) to ensure that risk aversion steps defined for the risk are being properly applied; and
(3) to collect information that can be used for future risk analysis.
Correct Answer: D
Question 144 Explanation:
Risk monitoring is a project tracking activity with three primary objectives:
(1) to assess whether predicted risks occur.
(2) to ensure that risk aversion steps defined for the risk are being properly applied; and
(3) to collect information that can be used for future risk analysis.
(1) to assess whether predicted risks occur.
(2) to ensure that risk aversion steps defined for the risk are being properly applied; and
(3) to collect information that can be used for future risk analysis.