Question 289
Software Risk estimation involves following two tasks :
A
risk magnitude and risk impact
B
risk probability and risk impact
C
risk maintenance and risk impact
D
risk development and risk impact
Question 289 Explanation: 
Software Risk estimation involves risk probability and risk impact.
Correct Answer: B
Question 289 Explanation: 
Software Risk estimation involves risk probability and risk impact.