Given a project wih an estimated effort of 1500 person-hours and a team of 5 people ,how many days will it to take to complete the project, if each person works 8 hours a day?
|
30
|
|
|
37.5
|
|
|
40
|
|
|
45.5
|
Correct Answer: B