Question 1 |
Which one of the following is the correct estimation model based on software equation?
E = [LOC×B0.222/P]2 × (1/t4) | |
E = [LOCxB0.333/P]3 * (1/t4) | |
E = [LOC*B0.444/P]4 x (1/t3) | |
E = [LOCxB0.111/P]6x (1/t3) |