Question 1
Which one of the following is the correct estimation model based on software equation?

A
E = [LOC×B0.222/P]2 × (1/t4)
B
E = [LOCxB0.333/P]3 * (1/t4)
C
E = [LOC*B0.444/P]4 x (1/t3)
D
E = [LOCxB0.111/P]6x (1/t3)