Question 1
An __________ chart is a project schedule representation that presents project plan as a directed graph. The critical path is the __________ sequence of ______________ tasks and it defines project _______________
A
Activity, Shortest, Independent, Cost
B
Activity, Longest, Dependent, Duration
C
Activity, Longest, Independent, Duration
D
Activity, Shortest, Dependent, Duration
Question 1 Explanation: 
The critical path method (CPM), or critical path analysis (CPA), is an algorithm for scheduling a set of project activities. It is commonly used in conjunction with the program evaluation and review technique (PERT). A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish
There is 1 question to complete.

Access quiz wise question and answers by becoming as a solutions adda PRO SUBSCRIBER with Ad-Free content

Register Now

If you have registered and made your payment please contact solutionsadda.in@gmail.com to get access