...
UPPCL AE 2022
October 8, 2023
NIC-NIELIT STA 2020
October 8, 2023
UPPCL AE 2022
October 8, 2023
NIC-NIELIT STA 2020
October 8, 2023

Software-Engineering

Question 17

Consider the CPM activity chart where an arc connecting two milestones is labeled with a task identifier and the time taken in days. For example in order to go from A to B, task T1 takes 180 days. A dashed line depicts an additional dependency that is equivalent to a zero time task.

The set of activities that lie on the critical path are

A
T1, T2, T8, T10
B
T1, T3, T8, T10
C
T1, T2, T3, T4, T5, T6, T7, T8, T9, T10
D
T1, T4, T5, T7, T8, T10
Question 17 Explanation: 
Note: Out of syllabus.
Correct Answer: D
Question 17 Explanation: 
Note: Out of syllabus.
0 0 votes
Article Rating
Subscribe
Notify of
0 Comments
Inline Feedbacks
View all comments
0
Would love your thoughts, please comment.x
()
x
error: Alert: Content selection is disabled!!