Question 22 |
Consider the CPM activity chart where an arc connecting two milestones is labeled with a task identifier and the time taken in days. For example in order to go from A to B, task T1 takes 180 days. A dashed line depicts an additional dependency that is equivalent to a zero time task.
The set of activities that lie on the critical path are
T1, T2, T8, T10 | |
T1, T3, T8, T10 | |
T1, T2, T3, T4, T5, T6, T7, T8, T9, T10 | |
T1, T4, T5, T7, T8, T10 |
Question 22 Explanation:
Note: Out of syllabus.
Correct Answer: D
Question 22 Explanation:
Note: Out of syllabus.