Question 12
|
Which one of the following is not a risk management technique for managing the risk due to unrealistic schedules and budgets ?
|
Detailed multi source cost and schedule estimation.
|
|
|
Design cost
|
|
|
Incremental development
|
|
|
Information hiding
|
Question 12 Explanation:
Information hiding is not a risk management technique for managing the risk due to unrealistic schedules and budgets.
Correct Answer: D