Question 219
COCOMO stands for
A
COmposite COst MOdel
B
COnstructive COst MOdel
C
COnstructive Composite MOdel
D
COmprehensive Construction MOdel
Question 219 Explanation: 
COCOMO stands for COnstructive COst MOdel. It is a procedural software cost estimation model but not software process model. Linear sequential,prototype and spiral models are software process models.
The basic COCOMO equations take the form
1. Effort Applied (E) = a(KLOC)b [ man-months ]
2. Development Time (D) = c(Effort Applied)d [months]
3. People required (P) = Effort Applied / Development Time [count]
Correct Answer: B
Question 219 Explanation: 
COCOMO stands for COnstructive COst MOdel. It is a procedural software cost estimation model but not software process model. Linear sequential,prototype and spiral models are software process models.
The basic COCOMO equations take the form
1. Effort Applied (E) = a(KLOC)b [ man-months ]
2. Development Time (D) = c(Effort Applied)d [months]
3. People required (P) = Effort Applied / Development Time [count]
0 0 votes
Article Rating
Subscribe
Notify of
0 Comments
Inline Feedbacks
View all comments
0
Would love your thoughts, please comment.x
()
x
error: Alert: Content selection is disabled!!