UGC NET CS 2013 June-paper-2

Question 1
COCOMO stands for
A
COmposite COst MOdel
B
COnstructive COst MOdel
C
COnstructive Composite MOdel
D
COmprehensive Construction MOdel
Question 1 Explanation: 
COCOMO stands for COnstructive COst MOdel. It is a procedural software cost estimation model but not software process model. Linear sequential,prototype and spiral models are software process models.
The basic COCOMO equations take the form
1. Effort Applied (E) = a(KLOC)b [ man-months ]
2. Development Time (D) = c(Effort Applied)d [months]
3. People required (P) = Effort Applied / Development Time [count]
Correct Answer: B
Question 1 Explanation: 
COCOMO stands for COnstructive COst MOdel. It is a procedural software cost estimation model but not software process model. Linear sequential,prototype and spiral models are software process models.
The basic COCOMO equations take the form
1. Effort Applied (E) = a(KLOC)b [ man-months ]
2. Development Time (D) = c(Effort Applied)d [months]
3. People required (P) = Effort Applied / Development Time [count]