Question 205
System development cost estimation with use-cases is problematic because :
A
of paucity of examples
B
the data can be totally incorrect
C
the expertise and resource available are not used
D
the problem is being over simplified
Question 205 Explanation: 
System development cost estimation with use-cases is problematic because the data can be totally incorrect.
Correct Answer: B
Question 205 Explanation: 
System development cost estimation with use-cases is problematic because the data can be totally incorrect.