Question 286
In software project planning, work Breakdown structure must be __________ .
A
A graph
B
A tree
C
A Eular​s graph
D
None of the above
Question 286 Explanation: 
Work Breakdown structure(WBS) must be tree. The tree structure will give overall view of a project. Normally we can divide two types of WBS
1. Functional WBS
2. Activity WBS
WBS tree structure:
Correct Answer: B