| Question 286 |
In software project planning, work Breakdown structure must be __________ .
| A graph | |
| A tree | |
| A Eulars graph | |
| None of the above |
Question 286 Explanation:
Work Breakdown structure(WBS) must be tree. The tree structure will give overall view of a project. Normally we can divide two types of WBS
1. Functional WBS
2. Activity WBS
WBS tree structure:
1. Functional WBS
2. Activity WBS
WBS tree structure:
Correct Answer: B