COCOMO-Model

Question 12
On an average, the programmer months is given by 3.6 * (KLOC)​ 1.2​ . If so, a project requiring one thousand source instructions will require
A
3.6PM
B
0.36PM
C
0.0036PM
D
7.23PM
Question 12 Explanation: 
Given programmer months is given by 3.6 * (KLOC)​ 1.2​ and lines of codes are 1000 =1K.
=3.6(1)​ 1.2​ =3.6 Programmer months.
Correct Answer: A
Question 12 Explanation: 
Given programmer months is given by 3.6 * (KLOC)​ 1.2​ and lines of codes are 1000 =1K.
=3.6(1)​ 1.2​ =3.6 Programmer months.