COCOMO-Model

Question 11
Estimation of software development effort for organic software in basic COCOMO is
A
E = 2.0(KLOC)1.05 Per Month
B
E = 3.4(KLOC)1.06 Per Month
C
E = 2.4(KLOC)1.05 Per Month
D
E = 2.4(KLOC)1.07 Per Month
Question 11 Explanation: 
The basic COCOMO equations take the form
1. Effort Applied (E) = ab(KLOC)bb [ man-months ]
2. Development Time (D) = cb(Effort Applied)db [months]
3. People required (P) = Effort Applied / Development Time [count]

where, KLOC is the estimated number of delivered lines (expressed in thousands ) of code for project. The constants ab, bb, cb and db are given in the following table (note: the values listed below are from the original analysis, with a modern reanalysis producing different values)

Correct Answer: C
Question 11 Explanation: 
The basic COCOMO equations take the form
1. Effort Applied (E) = ab(KLOC)bb [ man-months ]
2. Development Time (D) = cb(Effort Applied)db [months]
3. People required (P) = Effort Applied / Development Time [count]

where, KLOC is the estimated number of delivered lines (expressed in thousands ) of code for project. The constants ab, bb, cb and db are given in the following table (note: the values listed below are from the original analysis, with a modern reanalysis producing different values)

0 0 votes
Article Rating
Subscribe
Notify of
0 Comments
Inline Feedbacks
View all comments
0
Would love your thoughts, please comment.x
()
x
error: Alert: Content selection is disabled!!