COCOMO-Model

Question 4

In a software project, COCOMO (Constructive Cost Model) is used to estimate

A
effort, cost and schedule based on the size of the software
B
size and duration based on the effort of the software
C
effort and cost based on the duration of the software
D
size, effort and duration based on the cost of the software
Correct Answer: A