August 28, 2024COCOMO-Model
|
Question 4
|
In a software project, COCOMO (Constructive Cost Model) is used to estimate
|
effort, cost and schedule based on the size of the software
|
|
|
size and duration based on the effort of the software
|
|
|
effort and cost based on the duration of the software
|
|
|
size, effort and duration based on the cost of the software
|
Correct Answer: A