Data-Structures
October 12, 2023Software-Engineering
October 13, 2023Software-Engineering
Question 3 |
Assume that the delivered lines of code L of a software is related to the effort E in person months and duration t in calendar months by the relation L = P* (E/B)1/3 * t4/3, where P and B are two constants for the software process and skills factor. For a software project, the effort was estimated to be 20 person months and the duration was estimated to be 8 months. However, the customer asked the project team to complete the software project in 4 months. What would be the required effort in person months?
10 | |
40 | |
160 | |
320 |
Question 3 Explanation:
Note: Out of syllabus.
Correct Answer: D
Question 3 Explanation:
Note: Out of syllabus.
Subscribe
Login
0 Comments