In the Spiral model of software development, the primary determinant in selecting activities in each iteration is
Correct Answer: D
Question 1 Explanation:
Note: Out of syllabus.
Iteration size
Cost
Adopted process such as Rational Unified Process or Extreme Programming
Risk