Question 6925 – Engineering-Mathematics
April 8, 2024
Question 15323 – DSSSB PGT 2021
April 8, 2024
Question 6925 – Engineering-Mathematics
April 8, 2024
Question 15323 – DSSSB PGT 2021
April 8, 2024

Software-Engineering

Question 15

A software project has four phases P1, P2, P3 and P4. Of these phases, P1 Is the first one and needs to be completed before any other phase can commence. Phases P2 and P3 can be executed in parallel. Phase P4 cannot commence until both P2 and P3 are completed. The optimistic, most likely, and pessimistic estimates of the phase completion times in days, for Pl, P2, P3 and P4 are, respectively, (11, 15, 25), (7, 8, 15), (8, 9, 22), and (3, 8, 19).
The costs (in Rupees per day) of crashing the expected phase completion times for the four phases, respectively, are 100, 2000, 50, and 1000. Assume that the expected phase completion times of the phases cannot be crashed below their respective most likely completion times. The minimum and the maximum amounts (in Rupees) that can be spent on crashing so that ALL paths are critical are, respectively.

A
100 and 1000
B
100 and 1200
C
150 and 1200
D
200 and 2000
Question 15 Explanation: 
Note: Out of syllabus.
Correct Answer: D
Question 15 Explanation: 
Note: Out of syllabus.
0 0 votes
Article Rating
Subscribe
Notify of
0 Comments
Inline Feedbacks
View all comments
0
Would love your thoughts, please comment.x
()
x
error: Alert: Content selection is disabled!!