Software-Engineering
August 28, 2024Software-Engineering
August 28, 2024COCOMO-Model
|
Question 12
|
On an average, the programmer months is given by 3.6 * (KLOC) 1.2 . If so, a project requiring one thousand source instructions will require
|
3.6PM
|
|
|
0.36PM
|
|
|
0.0036PM
|
|
|
7.23PM
|
Question 12 Explanation:
Given programmer months is given by 3.6 * (KLOC) 1.2 and lines of codes are 1000 =1K.
=3.6(1) 1.2 =3.6 Programmer months.
=3.6(1) 1.2 =3.6 Programmer months.
Correct Answer: A
Question 12 Explanation:
Given programmer months is given by 3.6 * (KLOC) 1.2 and lines of codes are 1000 =1K.
=3.6(1) 1.2 =3.6 Programmer months.
=3.6(1) 1.2 =3.6 Programmer months.