| Question 409 |
In the Spiral model of software development, the primary determinant in selecting activities in each iteration is
| Iteration size | |
| Cost | |
| Adopted process such as Rational Unified Process or Extreme Programming | |
| Risk |
Question 409 Explanation:
→ In the Spiral model of software development, the primary determinant in selecting activities in each iteration is risk handling
→ The spiral model is a risk-driven software development process model. Based on the unique risk patterns of a given project, the spiral model guides a team to adopt elements of one or more process models, such as incremental, waterfall, or evolutionary prototyping.

→ The spiral model is a risk-driven software development process model. Based on the unique risk patterns of a given project, the spiral model guides a team to adopt elements of one or more process models, such as incremental, waterfall, or evolutionary prototyping.

Correct Answer: D
Question 409 Explanation:
→ In the Spiral model of software development, the primary determinant in selecting activities in each iteration is risk handling
→ The spiral model is a risk-driven software development process model. Based on the unique risk patterns of a given project, the spiral model guides a team to adopt elements of one or more process models, such as incremental, waterfall, or evolutionary prototyping.

→ The spiral model is a risk-driven software development process model. Based on the unique risk patterns of a given project, the spiral model guides a team to adopt elements of one or more process models, such as incremental, waterfall, or evolutionary prototyping.