| Question 225 |
Software risk estimation involves following two tasks :
| Risk magnitude and risk impact | |
| Risk probability and risk impact | |
| Risk maintenance and risk impact | |
| Risk development and risk impact |
Question 225 Explanation:
Software Risk estimation involves risk probability and risk impact.
→ Risk impact factors are
1. Negligible [low]
2. Marginal
3. Critical
4. Catastrophic [High]
→ Risk exposure:
RE=P*C
P=The probability of occurrence for a risk
C=The cost to the project should the risk actually occur
→ Risk impact factors are
1. Negligible [low]
2. Marginal
3. Critical
4. Catastrophic [High]
→ Risk exposure:
RE=P*C
P=The probability of occurrence for a risk
C=The cost to the project should the risk actually occur
Correct Answer: B
Question 225 Explanation:
Software Risk estimation involves risk probability and risk impact.
→ Risk impact factors are
1. Negligible [low]
2. Marginal
3. Critical
4. Catastrophic [High]
→ Risk exposure:
RE=P*C
P=The probability of occurrence for a risk
C=The cost to the project should the risk actually occur
→ Risk impact factors are
1. Negligible [low]
2. Marginal
3. Critical
4. Catastrophic [High]
→ Risk exposure:
RE=P*C
P=The probability of occurrence for a risk
C=The cost to the project should the risk actually occur