Question 225
Software risk estimation involves following two tasks :
A
Risk magnitude and risk impact
B
Risk probability and risk impact
C
Risk maintenance and risk impact
D
Risk development and risk impact
Question 225 Explanation: 
Software Risk estimation involves risk probability and risk impact.
Risk impact factors are
1. Negligible [low]
2. Marginal
3. Critical
4. Catastrophic [High]
Risk exposure:
RE=P*C
P=The probability of occurrence for a risk
C=The cost to the project should the risk actually occur
Correct Answer: B
Question 225 Explanation: 
Software Risk estimation involves risk probability and risk impact.
Risk impact factors are
1. Negligible [low]
2. Marginal
3. Critical
4. Catastrophic [High]
Risk exposure:
RE=P*C
P=The probability of occurrence for a risk
C=The cost to the project should the risk actually occur